New City Offices

  1. Current Project Information
  2. About New City Offices
  3. Construction Information
  4. Project Financials
  5. Design and Site Plan
  6. Galena Plaza Outreach
  7. Stay Informed

Project Update - June 22, 2020

There is a lot of coordinated activity on the new city offices job site including concrete work, sidewalk installation and continued steel erection. Vertical construction is tracking well.

The week of June 29, the crane will be moved on the north side of the building and crews will take steps to reopen the Rio Grande Parking Garage to full capacity before the July 4 weekend. On Thursday, July 2, it is anticipated that the northwest parking garage access and garage stair will reopen for use. 

View Rio Grande Parking Garage and Site Area Map. >>

Crane Operations

Construction crews have mobilized the crane for vertical construction to lift and place girders and other structural building elements. The crane is anticipated to be on-site through August.

Rio Grande Parking Garage

Beginning May 19 through mid-June, the northwest stairs of the Rio Grande Parking Garage will be closed. For alternate access, use the east stairs, elevator, or Jail Trail. Both entrances to the parking garage are open.

City Offices Construction and COVID-19 Site Safety Measures

Crews continue to make progress on critical path construction activities including work on the foundational and structural elements of the new building. The job site is open with limited contractors and minimal crew members.

The Aspen City Offices team is dedicated to public safety and the safety of construction crews and will continue to adhere to state and local COVID-19 operational recommendations and regulations as the situation evolves.

Staircase Closure through summer 2021

The blue staircase connecting Rio Grande Place and the plaza (staircase east of the parking garage/plaza) is closed through summer 2021. For alternate access, use Jail Trail or the parking garage elevator.

View map >>