rendering

City Offices Construction Update for October 7, 2019

  • Crews recently completed shoring and micropile construction for the new City offices foundation.
  • Excavation activities and stairway deconstruction are ongoing. Excavation activities and heavy truck traffic in and out of the site will continue through November.
  • Next week the Mill Street sidewalk replacement is anticipated to be complete.
  • Later this month, crews will begin construction on the new foundation footings and walls.
  • View work activities and anticipated impacts for October 2019 [PDF].

Rio Grande Parking Garage

Parking garage users should continue to enter the parking garage via N. Mill St. (upper/west entrance) and exit via Rio Grande Pl. (lower/north exit) to Mill St. or to Spring St. The lower garage entrance is anticipated to reopen in the next couple weeks.

Schedule and routes are approximate, weather dependent and subject to change. Business and pedestrian access remains open with some pedestrian detours in place. Please follow signage and flagger instructions.

Neighborhood BBQ – Wednesday, October 9


Please join the City offices project team for a neighborhood barbeque on Wednesday, October 9 from 11:30 AM - 12:30 PM on the Galena Plaza Lawn.

construction site photo
Crews make progress on the new Aspen City offices project - September 23, 2019

Reminder: Staircase Closure through summer 2021

The blue staircase connecting Rio Grande Place and the plaza (staircase east of the parking garage/plaza) is closed and remain closed for the next two years. For alternate access, use Jail Trail or the parking garage elevator.


Public Information


Email: newcityoffices@cityofaspen.com
 
Webpage: www.cityofaspen.com/newcityoffices
 
24-Hour Hotline: 970-429-1793